Group | Milestone Number (As Listed) | New Milestone Number | Description | Expected Completion | Actual Completion |
---|---|---|---|---|---|
NA1 | MN1.1 | M-NA1.1 | Conclusion of the Cons. Agreement 1) | -3 | 8 |
NA1 | MN1.2 | M-NA1.2 | Appointment of the project manager 2) | 0 | 8 |
NA1 | MN1.3 | M-NA1.3 | Appointment of the administrative assistant 3) | 0 | 1 |
NA2 | EVN-NREN | M-NA2.1 | chair attends EXPReS Board Meeting No. 1 4) | 2 | 8 |
NA2 | EVN-NREN | M-NA2.2 | chair attends EXPReS Consortium Board Meeting No. 2 | 14 | |
NA2 | EVN-NREN | M-NA2.3 | chair attends EXPReS Board Meeting No. 3 | 26 | |
NA3 | EVSAG | M-NA3.1 | chair attends EXPReS Consortium Board Meeting 5) | 2 | |
NA3 | EVSAG | M-NA3.2 | chair attends EXPReS Consortium Board Meeting | 14 | |
NA3 | EVSAG | M-NA3.3 | chair attends EXPReS Consortium Board Meeting | 26 | |
NA4 | NA4.i | M-NA4.1 | The EXPReS web-site goes public and on-line | not listed | 1 |
NA4 | NA4.ii | M-NA4.2 | Management tools are added to the web-site and used effectively for Project management | not listed | 6 |
NA4 | NA4.iii | M-NA4.3 | the first PR material is produced and presented at the first iGRID networking event 6) 7) | not listed | n/a |
NA4 | NA4.iv | M-NA4.4 | EXPReS participates in annual public open-days at JIVE and the other partner institutes involved in such outreach activities 8) | not listed | 8 |
NA4 | NA4.v | M-NA4.5 | Press release announcing the EXPReS e-VLBI facility as an open, production-level facility open to all astronomers. Other milestones include: the appointment of the EXPReS Outreach Officer. | not listed | |
SA1 | MSA1.1 | M-SA1.1 | Call for Proposals for e-VLBI service | 1 | ongoing 9) |
SA1 | MSA1.2 | M-SA1.2 | Preliminary e-VLBI Service | 4 | |
SA1 | MSA1.3 | M-SA1.3 | Basic data-link technology | 6 | |
SA1 | MSA1.4 | M-SA1.4 | Basic VLBI elements adapted for e-VLBI | 6 | |
SA1 | MSA1.5 | M-SA1.5 | Enhanced ToO support | 17 | |
SA1 | MSA1.6 | M-SA1.6 | Enhanced e-VLBI Service | 18 | |
SA1 | MSA1.7 | M-SA1.7 | Enhanced ToO support | 22 | |
SA1 | MSA1.8 | M-SA1.8 | Adaptive network utilization | 22 | |
SA1 | MSA1.6b | M-SA1.9 | Full bandwidth utilization (duplicate number) | 24 | |
SA1 | MSA1.7b | M-SA1.10 | Live e-VLBI system monitoring (duplicate number) | 24 | |
SA1 | MSA1.8b | M-SA1.11 | Full e-VLBI Service (duplicate number) | 24 | |
SA2 | M1: | M-SA2.1 | Feasibility study of the last-mile connection to the nearest GÉANT node. | To + 6 months. | |
SA2 | M2: | M-SA2.2 | Construction and equipment of the last-mile infrastructure. | To + 18 months. | |
SA2 | M3: | M-SA2.3 | e-VLBI Fringes (Detection). | To +10 months. | |
JRA1 | DJ1.1 | M-JRA1.1 | Requirements document data acquisition | not listed | |
JRA1 | DJ1.2 | M-JRA1.2 | Strategic document broadband protocols | not listed | |
JRA1 | DJ1.4 | M-JRA1.3 | Design document correlator algorithms | not listed | |
JRA1 | DJ1.6 | M-JRA1.4 | eVLBI - Grid design document | not listed | |
JRA1 | DJ1.5 | M-JRA1.5 | overall design document DJ1.5, which will describe all the interfaces in the project. | not listed |