Deliverables
Deliverable # | Activity # | Deliverable title | Lead Participant | Planned Delivery month | Actual Delivery Month | Current Status |
---|---|---|---|---|---|---|
D1 | NA4 | Creation of Public EXPReS web-site | JIVE | 2 | ||
D2 | JRA1 | Data acquisition requirements document | MRO | 2 | ||
D3 | JRA1 | Protocols strategic document | JBO | 2 | ||
D4 | NA2 | EVN-NREN meeting No. 1 (under auspices of EXPReS) | DANTE | 3 | ||
D5 | SA1 | Central data link control | JIVE | 3 | ||
D6 | NA3 | First meeting of eVSAG under auspices of EXPReS | OSO | 4 | ||
D7 | NA4 | Creation of EXPReS web-based management tools | JIVE | 4 | ||
D8 | JRA1 | Visualization software | JIVE | 4 | ||
D9 | JRA1 | Correlator design specification | JIVE | 5 | ||
D10 | NA4 | Generation of PR material (phase 1) | 6 | |||
D11 | SA1 | Job preparation utilities | JIVE | 6 | ||
D12 | SA1 | Fast/adaptive scheduling tools | JIVE | 6 | ||
D13 | SA2 | Feasibility study of the last-mile connection to the nearest GÉANT node for participant CNIG-IGN | CNIG-IGN | 6 | ||
D14 | SA2 | Feasibility study of the last-mile connection to the nearest GÉANT node for participant MPIfR | MPIfR | 6 | ||
D15 | SA2 | Equipment of the last-mile infrastructure for participant INAF (telescope in Medicina) | INAF | 6 | ||
D16 | SA2 | Feasibility study of the last-mile connections to the nearest GÉANT node for participant CAS (Shanghai, Urumqi, Miyun, Yunnan ) | CAS | 6 | ||
D17 | SA2 | Feasibility study of the last-mile connection to the nearest GÉANT node for participant VIRAC | VIRAC | 6 | ||
D18 | SA2 | Feasibility study of the last-mile connection to the nearest GÉANT node for participant HRAO | HRAO | 6 | ||
D19 | SA2 | Feasibility study of the last-mile connection to the nearest GÉANT node for participant NAIC (Arecibo) | NAIC | 6 | ||
D20 | SA2 | Feasibility study of the last-mile connection to the nearest GÉANT node for participant TIGO | TIGO | 6 | ||
D21 | SA2 | Feasibility study of the last-mile connection to AARNET for participant CSIRO | AARNET | 6 | ||
D22 | JRA1 | Overall design document | ALL | 6 | ||
D23 | JRA1 | eVLBI-Grid design document | PSNC | 6 | ||
D24 | JRA1 | eVLBI fringes PC-EVN | OSO | 7 | ||
D25 | JRA1 | LOFAR connection strategic document | ASTRON | 7 | ||
D26 | JRA1 | Data acquisition design document | MRO | 8 | ||
D27 | SA1 | eMERLIN VSI interfaces design | UniMan | 9 | ||
D28 | SA1 | Selective data processor controls | JIVE | 9 | ||
D29 | SA2 | e-VLBI test observations, Medicina | INAF | 10 | ||
D30 | JRA1 | eVLBI-Grid interface document | OSNC | 10 | ||
D31 | NA2 | NA2 annual report No. 2 (as part of EXPReS Ann. Rep No. 2) | JIVE | 24 | ||
D32 | NA1 | Annual report (incl. Financial information) to EC | JIVE | 12 | ||
D33 | NA2 | NA2 annual report No. 1 (as part of EXPReS Ann. Rep No. 1) | JIVE | 12 | ||
D34 | NA4 | e-VLBI Demonstration and attendance at Network events. | JIVE | 12 | ||
D35 | SA1 | Network protocol decision | JIVE | 12 | ||
D36 | SA1 | Monitored information handling modules | JIVE | 12 | ||
D37 | SA2 | Equipment of the last-mile infrastructure for participant MRO | MRO | 12 | ||
D38 | SA2 | Construction and equipment of the last-mile infrastructure for participant CNIG-IGN | CNIG-IGN | 12 | ||
D39 | SA2 | Construction and equipment of the last-mile infrastructure for participant MPIfR | MPIfR | 12 | ||
D40 | SA1 | Monitoring processes | JIVE | 12 | ||
D41 | JRA1 | Protocols performance report | JBO | 13 | ||
D42 | JRA1 | Software correlator core | JIVE | 14 | ||
D43 | JRA1 | Software data product | JIVE | 15 | ||
D44 | SA1 | Real-time data processor control software | JIVE | 15 | ||
D45 | SA1 | Tests using local Jodrell Bank home e-MERLIN telescope | UniMan | 15 | ||
D46 | NA3 | eVSAG meeting No. 2 | OSO | 16 | ||
D47 | SA1 | Real-time Pipeline | JIVE | 16 | ||
D48 | NA2 | EVN-NREN meeting No. 2 | JIVE | 18 | ||
D49 | NA4 | Generation of new PR material (phase 2) | DANTE | 18 | ||
D50 | SA1 | Visibility monitor | JIVE | 18 | ||
D51 | SA1 | Tested software for operational improvements | JIVE | 18 | ||
D52 | SA1 | Test using remote e-MERLIN telescope | UniMan | 18 | ||
D53 | SA1 | VSI support software | JIVE | 18 | ||
D54 | SA1 | VSI Interfaces | JIVE | 12 | ||
D55 | SA2 | 10 Gbps link upgrade between MERLIN and JIVE | MERLIN, JIVE | 18 | ||
D56 | SA2 | e-VLBI test observations, Metsahovi | MRO | 18 | ||
D57 | SA2 | Construction and equipment of the last-mile infrastructure for participant Shanghai | CAS | 18 | ||
D58 | SA2 | Construction and equipment of the last-mile infrastructure in AARNET to allow connection of participant CSIRO | AARNET, CSIRO | 18 | ||
D59 | SA2 | Construction and equipment of the last-mile infrastructure for participant Urumqi | CAS | 18 | ||
D60 | SA2 | Construction and equipment of the last-mile infrastructure for participant Miyun | CAS | 18 | ||
D61 | SA2 | Construction and equipment of the last-mile infrastructure for participant Kunming | CAS | 18 | ||
D62 | SA2 | Construction and equipment of the last-mile infrastructure for participant VIRAC | VIRAC | 18 | ||
D63 | SA2 | Equipment of the last-mile infrastructure for participant NAIC | NAIC | 18 | ||
D64 | SA2 | Construction and equipment of the last-mile infrastructure for participant TIGO | TIGO | 18 | ||
D65 | SA2 | AARNET connectivity enhancements | AARNET | 18 | ||
D66 | JRA1 | Data acquisition interface document | MPI | 18 | ||
D67 | JRA1 | LOFAR station interface report | ASTRON | 18 | ||
D68 | JRA1 | Software for workflow management | PSNC | 18 | ||
D69 | SA2 | Feasibility study of the last-mile connection to the nearest GÉANT node for participant INAF (Sardinia) | INAF | 20 | ||
D70 | SA2 | 10 Gbps link between UniMan and OSO for ultra-VLBI tests | UniMan, OSO | 20 | ||
D71 | SA1 | Flexible local GE network | JIVE | 21 | ||
D72 | SA2 | e-VLBI test observations, Effelsberg | MPIfR | 21 | ||
D73 | SA2 | e-VLBI test observations, Metsahovi | ATNF | 22 | ||
D74 | SA2 | e-VLBI test observations, Yebes | OAN | 22 | ||
D75 | JRA1 | Software for correlation on cluster | JIVE | 23 | ||
D76 | JRA1 | Data acquisition test report | MPI | 23 | ||
D77 | JRA1 | Data acquisition prototype at telescope | OSO | 23 | ||
D78 | JRA1 | Overall broadband demonstration | JIVE | 23 | ||
D79 | JRA1 | Software cluster correlation | JIVE | 23 | ||
D80 | JRA1 | First fringes software correlator | JIVE | 23 | ||
D81 | NA1 | Annual report (incl. Financial information) to EC | JIVE | 24 | ||
D82 | NA2 | NA2 annual report No. 2 (as part of EXPReS Ann. Rep No. 2) | JIVE | 24 | ||
D83 | NA4 | e-VLBI Demonstration and attendance at Network events. | 24 | |||
D84 | SA1 | Network monitoring tools | JIVE | 24 | ||
D85 | SA1 | Multiple e-MERLIN telescope tests | UniMan | 24 | ||
D86 | SA2 | Construction and equipment of the last-mile infrastructure for participant HartRAO | HRAO | 24 | ||
D87 | JRA1 | Software to collect distributed output | JIVE | 24 | ||
D88 | NA2 | EVN-NREN meeting No. 3 | DANTE | 26 | ||
D89 | NA2 | EVN-NREN representatives present EXPReS networking results at the e-VLBI Science & Technology Workshop | DANTE | 26 | ||
D90 | NA2 | EVN-NREN meeting | DANTE | |||
D91 | NA3 | eVSAG meeting No. 3 | OSO | 26 | ||
D92 | JRA1 | Software to create data product from distributed correlation | JIVE | 27 | ||
D93 | JRA1 | Software routing | PSNC | 29 | ||
D94 | NA3 | e-VLBI Workshop held in Onsala | 30 | |||
D95 | SA1 | Improved network applications | JIVE | 30 | ||
D96 | SA1 | Monitoring user interfaces | JIVE | 30 | ||
D97 | SA2 | e-VLBI test observations, Urunqi | CAS | 30 | ||
D98 | SA2 | e-VLBI test observations, Mijun | CAS | 30 | ||
D99 | SA2 | e-VLBI test observations, Kunming | CAS | 30 | ||
D100 | SA2 | e-VLBI test observations, VIRAC | VIRAC | 30 | ||
D101 | SA2 | e-VLBI test observations, HRAO | HRAO | 30 | ||
D102 | SA2 | e-VLBI test observations, NAIC, Arecibo | NAIC | 30 | ||
D103 | SA2 | e-VLBI test observations, TIGO | TIGO | 30 | ||
D104 | SA2 | Construction and equipment of the last-mile infrastructure for participant INAF (Sardinia) | INAF | 30 | ||
D105 | JRA1 | eMERLIN interface available | JBO | 30 | ||
D106 | JRA1 | Fringes with new routing | JIVE | 31 | ||
D107 | NA3 | Publication of e-VLBI Workshop proceedings | OSO | 32 | ||
D108 | JRA1 | Software distributed correlation | JIVE | 33 | ||
D109 | JRA1 | First fringes Grid correlator | JIVE | 34 | ||
D110 | JRA1 | First fringes on FABRIC | JIVE | 35 | ||
D111 | NA1 | Annual report (incl. Financial information) to EC | JIVE | 36 | ||
D112 | NA1 | Final Report to Board and EC | JIVE | 36 | ||
D113 | NA1 | Final Plan for using and disseminating knowledge | JIVE | 36 | ||
D114 | NA1 | Implementation of the Gender Action Plan | JIVE | 36 | ||
D115 | NA1 | Raising public participation and awareness | JIVE | 36 | ||
D116 | NA2 | NA2 annual & Final reports | JIVE | 36 | ||
D117 | NA4 | e-VLBI Demonstration and attendance at network events. | JIVE | 36 | ||
D118 | JRA1 | Final report | JIVE | 36 |